Sindhuli, June 13 -- Seven years into construction, progress on the Madan Bhandari Highway, a national pride project, remains slow, with only 51 percent of the work completed so far. Around 1.5 kilome... Read More
Kathmandu, May 21 -- The Piplamod section of the Nagdhunga-Naubise road will remain closed from 10.30 am to 3 pm for 15 days starting Saturday, as road construction and improvement work resumes. Acco... Read More
Kathmandu, April 15 -- The geological study for the Kerung-Kathmandu railway, supported by China's technical and financial assistance, has entered its final phase. The study spans three districts: Ka... Read More
Kathmandu, March 25 -- The 80.33 km stretch of the Prithvi Highway from Abukhaireni to Pokhara has seen 67 percent overall progress, with work ongoing in various sections. However, the contract for th... Read More
Kathmandu, March 24 -- Locals have obstructed work on the Nagdhunga-Sisnekhola Tunnelway for the past nine days, demanding proper management of their already fulfilled demands. Construction on both th... Read More