Italy, Feb. 24 -- RWE has commissioned its first solar plant in Italy. The 8.3 megawatt (MWac) Bosco groundmounted solar plant consists of around 15,000 bifacial modules. The photovoltaic plant is located on a 16 hectare site in the municipality of Partinico near Palermo, Sicily, and will supply up to 7,000 Italian households with green electricity. Thanks to the implementation of a new accelerated permitting process in Italy, RWE was able to achieve Ready to Build in less than 18 months. Construction took around ten months. In order to optimise the use of land and resources, as well as to tackle grid scarcity, the Bosco solar plant uses the existing nearby RWE substation in Partinico, from which the local RWE wind farms already feed green ...