Nordseecluster offshore wind project reaches important milestone: first monopile foundation successfully installed off the German coast
Germany, July 28 -- The Nordseecluster offshore wind project has reached a significant milestone: the first turbine foundation has been successfully installed around 50 kilometres north of the German island of Juist.The monopiles were shipped from the heavy-lift terminal in Eemshaven, the Netherlands, to the construction site in the German North Sea by Van Oord's brand-new offshore installation vessel Boreas. Four monopiles can be loaded in one shipment. Each monopile foundation measures 85 metres in length and weighs approximately 1,500 metric tons, which is roughly equivalent to the weight of 1,000 small cars.Rather than using a monopile foundation topped with an overlapping separate transition piece, extended single monopiles are install...