Konecranes to deliver 39 cranes to Hitachi Energy's new transformer factory in Finland
Finland, July 2 -- Konecranes has received an order to supply 39 industrial cranes, with lifting capacities ranging from a couple of tons to several hundred of tons, to Hitachi Energy's new transformer manufacturing facility in Mustasaari, Finland. The order includes four SMARTON cranes, 21 Konecranes S-series, and 14 Konecranes CXT overhead cranes, all designed to meet the demanding requirements of heavy transformer production. The contract was booked in April 2025, with deliveries scheduled for completion by the end of 2026.Hitachi Energy is the world's largest transformer manufacturer by installed base and portfolio range. The new production and technology center-Hitachi Energy Park, located in the Vaasa region-will house a state-of-the-...