Foundation installation works completed at Denmark's largest offshore wind farm
Germany, Nov. 11 -- RWE has completed the installation of the foundations for the 1.1-gigawatt Thor offshore wind farm in the Danish North Sea. In September, the final of 72 monopiles for the wind turbines was installed. At the end of last week, RWE finalised the installation of the associated secondary steel structures - including boat landings, main access platforms, and internal cassettes. The completion of the secondary steel installation was achieved in less than six months using Van Oord's offshore wind installation vessel, MPI Adventure. Offshore works were coordinated from the Danish Port of Thyboron. To protect the foundations from the harsh conditions at sea until the turbine towers are mounted, innovative reusable hard covers hav...