DEME completes installation of first offshore substation for Coastal Virginia Offshore Wind project
United States, March 14 -- DEME has completed the installation of the first of three offshore substations for the 2.6 GW Coastal Virginia Offshore Wind (CVOW) project, located 43 kilometers off the coast of Virginia Beach, USA, according to the company's release.The installation involved a 3,907-metric tonne lift, placing the topside onto a jacket previously installed by DEME.The first substation arrived at the Portsmouth Marine Terminal in January 2024, following the installation of four pin piles for one offshore substation jacket last year during the initial campaign.DEME's DP3 installation vessel Orion will now proceed with installing transition pieces (TPs) before starting the second campaign of monopile installation.In 2021, a consort...