United States, Feb. 12 -- C.J. Mahan Construction Co. LLC, Urbancrest, Ohio, was awarded a firm-fixed-price contract for the Chickamauga Lock Approach Walls and Decommissioning Project. The amount of this action is $192,143,925, with a total cumulative face value of $558,374,213. Bids were solicited via the internet with one received. Work will be performed in Chattanooga, Tennessee, with an estimated completion date of March 9, 2029. Fiscal 2022 civil construction funds in the amount of $192,143,925 were obligated at the time of the award. U.S. Army Corps of Engineers, Nashville District, is the contracting activity (W912P5-26-C-A002).

Published by HT Digital Content Services with permission from Pivotal Sources....