India, Aug. 6 -- The Noida authority has blacklisted an agency, engaged in development of the International Golf Course in Sector 151A, for delaying the project work and also failing to carry out the developmental work as per the requisite norms, officials said on Tuesday.

The authority has decided to finalise another contractor to complete the project, with about 30% of the work yet to be completed, they added.

The step followed Noida authority's chief executive officer Lokesh M last week conducting a site inspection in Sector 151A last week, and pulling up the agency staff for delay, and violation of the construction guidelines.

"The authority has decided to seize the security amount of this agency named Kashyapi Infrastructure Priva...