New Delhi, April 26 -- The multilevel parking facility in west Delhi's Punjabi Bagh is nearing completion and is likely to be made operational for public next month, senior MCD officials said, adding that 97% of the work is already completed.

Built at a cost of Rs.31 crore, the project has a five-storey puzzle parking structure and can accommodate 225 cars at a time. Officials said the parking facility will help in decongestion of a key intersection in the area.

An MCD official said necessary no objection certificates (NOCs) are remaining to be obtained along with the basic finishing work to be done before it can be made functional. Foundation stone for the project was laid in July 2022 and it was scheduled to be completed in July 2024....