India, Sept. 27 -- The Noida authority officials in an inspection found out that a pipeline laid nearly 20 years ago is missing in several stretches, which will lead to delay in supplying Ganga water to Jaypee Wishtown housing projects.
As per an Allahabad High Court order, the authority was expected to ensure Ganga supply to the societies within two weeks after the Suraksha Group - which is managing Jaypee Infratech Limited (JIL) under the insolvency process - deposits Rs.60 crore. The money was submitted last week, officials said.
However, the authority is now planning fresh pipeline work for the water supply project and starting the supply by October 10, officials said.
"We fought a case in Allahabad High Court, made our builder dep...