India, Oct. 10 -- The contractor for the Gurugram metro project has begun mobilising the casting yard site in Sector 33, with a project office now set up and initial groundwork underway. The site was handed over to Gurugram Metro Rail Limited (GMRL) on a temporary basis.

Mobilising a site means preparing all the necessary resources, equipment and manpower at a site before the construction begins. It is a important step towards successful execution of a project.

Vaishali Singh, administrator, Haryana Shahari Vikas Pradhikaran (HSVP) visited the site on Wednesday morning along with GMRL officials to assess the readiness and progress of the land. A senior HSVP official said that during the visit, Singh issued directions to truck operators ...