India, Jan. 6 -- The Common Effluent Treatment Plant (CETP), planned for treating industrial wastewater in sector 34-35, will now be built by the Haryana State Industrial and Infrastructure Development Corporation (HSIIDC), district administration officials said.

Earlier, the Gurugram Metropolitan Development (GMDA) had consulted a private firm to prepare a detailed project report (DPR) for the plant in 2025, said officials.

A senior HSIIDC official said a new DPR is under review for the CETP in sector 34/35 and 37. "The project is expected to be completed by December 2027. The industrial units in the area along the Badshahpur drain passing through sector 34 will be covered in the project," the senior official said.

Officials said that...