India, July 10 -- After four days of disruptions, power supply to Hinjewadi and surrounding industrial areas has been fully restored as Maharashtra State Electricity Transmission Company Ltd (MSETCL) completed repair work in the 220 kV Infosys-Pegasus high-voltage cable on Wednesday.
The work was completed at 12:40 pm, bringing relief to over 52,000 low-tension consumers and nearly 100 high-tension industrial units, including IT giants Infosys and Nextra.
On July 6, MSETCL had scheduled a routine maintenance shutdown of the Hinjewadi and Pegasus substations from 11 am to 1 pm. However, at 2:10 pm, a critical fault occurred near the Hinjewadi Metro station in the Infosys-Pegasus transmission line, triggering a major power outage across t...