NOIDA, Jan. 28 -- The Lucknow bench of the Allahabad high court has dismissed a batch of petitions filed by Gaursons Hi-Tech Infrastructure and refused to interfere with orders passed by the Uttar Pradesh Real Estate Regulatory Authority (UP-Rera) and the Real Estate Appellate Tribunal (REAT) in favour of shop buyers at the developer's Gaur City Centre project in Greater Noida West.

In four similar cases, Justice Prashant Kumar upheld the findings that the project remained incomplete well beyond the committed timelines and that buyers were entitled to possession along with statutory interest for the delay.

The appeals were reserved on November 26, 2025, and pronounced on January 21.

Manoj Gaur, promoter of the Gaur City Centre project,...