India, June 17 -- The flood relief and infrastructure works by Maharashtra Industrial Development Corporation (MIDC) and Maha-Metro Line-3 contractor Tata Projects is going on despite the June 15 deadline set by Pune Metropolitan Region Development Authority (PMRDA) commissioner Yogesh Mhase following severe waterlogging in Hinjewadi on June 7.

PMRDA and MIDC officials conducted a joint review meeting and inspected the affected areas on Monday.

Heavy waterlogging on June 7 and June 13 turned Hinjewadi IT Park roads into flood zones. MIDC inspection found that barricades installed by the metro authorities in the middle of roads had blocked natural rainwater flow, leading to flooding on one side. The barricades were removed the next day....