India, June 3 -- The structural works at the key Vapi station in Gujarat along the 508-km Mumbai-Ahmedabad High-Speed Rail Corridor, popularly known as the bullet train project, have achieved key milestones, with the completion of rail platform level slab casting and structural steel installation, the implementing agency said.
The National High Speed Rail Corporation Limited (NHSRCL), which is implementing the project using Japanese Shinkansen technology, said roof sheeting and electrical installations were in progress. In a statement, it added that the station's approach viaduct toward Ahmedabad is ready, and work on that towards Mumbai was going on.
The NHSRCL said the Vapi station in Dungra village will have a 28,917 square metres bu...