India, Jan. 21 -- Belasis Flyover, a key east-west connector linking Tardeo, Nagpada and Mumbai Central Station, has been completed in a record time of just 15 months and six days, well ahead of its scheduled finish in May.
Situated on Jehangir Boman Behram Marg, formerly known as Belasis Road, the flyover's reopening will restore the east-west traffic movement that was disrupted for nearly two years, and is expected to ease congestion on Jahangir Boman Behram Marg, Dadasaheb Bhadkamkar Marg (Grant Road), Patthe Bapurao Marg and the Mahalaxmi Station bridge.
The work order for the flyover was issued in September 2024, with construction commencing on October 1, 2024. While work over the railway tracks was carried out by the railway depar...