India, April 3 -- Water supply will remain erratic in large parts of the city on Monday and Tuesday as the Gurugram Metropolitan Development Authority (GMDA) has planned a 30-hour- long shutdown of supply to connect its newly constructed water treatment plant (WTP) with water pipelines at Chandu Budhera, GMDA officials said.
They said they have already started the work of installing the pipelines but it will take them around 30 hours to completely connect the newly constructed 100mld water treatment plant with the existing supply system.
"It is informed that the work of connection of additional 100mld WTP Phase-IV to the existing 1600mm diameter pipeline at WTP Chandu Budhera by the Gurugram Metropolitan Development Authority (GMDA) wil...