Chandigarh, June 11 -- The structural work of the upcoming 800 MW unit of Deenbandhu Chhotu Ram Thermal Power Plant (DCRTPP) in Yamunanagar would be completed by July 15. The civil work for the critical curtain wall separating the new unit from the existing 2x300 MW units is expected to be completed by the end of June.
This was stated by Haryana Power Generation Corporation Ltd (HPGCL) chairman Sanjeev Kaushal at a high-level review meeting with officials from Bharat Heavy Electricals Limited (BHEL) to assess the progress of the 800 MW expansion unit. The Rs.7,272 crore project, awarded to BHEL on an engineering, procurement and construction basis has achieved several key milestones on the ground.
The HPGCL chairman said that a major op...