Lalitpur, Oct. 9 -- Construction of the four-lane flyover project at the Gwarko intersection in Lalitpur, one of the busiest intersections along the Ring Road has been stalled for the last four months, causing increasing traffic congestion along the busy Koteshwar-Kalanki road section. The project, which began in February 2022, has faced significant delays due to technical issues and the monsoon season, leaving the flyover incomplete and commuters frustrated.
According to the Quality Research and Development Centre under the Department of Roads, construction halted in the last week of May after the monsoon rains began, preventing the critical task of filling the ramp with a gravel-soil mixture. Director Prabhat Kumar Jha stated that the ...