Dar es Salaam, Jan. 16 -- THE Tanzania Electric Supply Company Limited (TANESCO) has restarted the tendering process for execution of Kinyerezi I Extension project following an order from the Public Procurement Regulatory Authority (PPRA).

The PPRA in December last year ordered TANESCO to restart the tender process after the previous tender process, which picked the CSI Energy Group (Tanzania) Limited last November to undertake the works, was disputed.

The restart of the process came after Aqua Power Tanzania Limited, whose bid was ranked second, challenged the award at PPRA in December last year.

The protest from Aqua Power Tanzania Limited was based on the fact that Ms CSI Energy Group failed to comply with a crucial tender requireme...