Jakarta, July 31 -- State-owned construction firm PT PP (Persero) Tbk (PTPP) is accelerating the development of Section 3 of the Probowangi Toll Road Project, which is now 79.13 percent complete and is expected to be ready within the deadline of 912 days.

Despite steady progress, one of the main challenges to the project's development is that the toll road route intersects the high-voltage Java-Bali transmission line, PTPP corporate secretary Joko Raharjo informed.

"Our project team successfully relocated several inter-island transmission towers through close cross-sector coordination. This reflects PTPP's technical capabilities and synergy in handling complex field challenges," he said in a statement issued from Jakarta on Thursday.

H...