Semarang, July 5 -- Central Java is set to have floating solar power plants (PLTS) at two locations: Kedungombgo in Sragen District and Gajahmungkur in Wonogiri District.

Director of Business Development and Commerce of PT PLN Indonesia Power, Julita Indah, stated in Semarang on Saturday that construction of the PLTS is included in the National Strategic Project (PSN).

Construction of the PLTS is targeted to begin in 2025, with a construction period of approximately 14 months, and each power plant is projected to generate 100 megawatts.

"The construction of the PLTS will not take long. We hope to start 'commercial operations' by late 2026 or early 2027," she remarked.