Dong Thap, July 21 -- Prime Minister Pham Minh Chinh on July 21 inspected the construction progress of two major expressway projects in the Mekong Delta, namely Chau Doc - Can Tho - Soc Trang and Cao Lanh - An Huu, and removed obstacles facing them. The Chau Doc - Can Tho - Soc Trang expressway, spanning 188.2 km, runs through four provinces and is being developed in phases as a four-lane route. Groundbreaking took place on June 17, 2023, with substantial completion targeted for 2026 and full operation expected by 2027. The expressway consists of four independent sub-projects, each managed by the respective provincial authority. During his field visit, PM Chinh examined Package No. 42 of Sub-project 1 under Phase 1, which runs through An ...