Khanh Hoa, Nov. 19 -- Khanh Hoa province is expediting site handover for Nuclear Power Plant Projects 1 and 2, aiming to complete site clearance and transfer land to investors before December 31 in line with the Prime Minister's directive.

On July 19, 2025, the Prime Minister issued Decision No. 1566/QD-TTg allocating 3.236 trillion VND (122.6 USD) to Khanh Hoa to implement resettlement and site-clearance work. Following a review, the provincial People's Committee has asked the Ministry of Finance (MoF) to consider allocating the remaining 9.156 trillion VND from the 2025 central budget to complete the resettlement scheme.

According to Decision No. 794/QD-TTg, the total planned land recovery area is 1,279.52 ha, affecting 1,288 househol...