Tashkent, Dec. 5 -- Tunneling works have been completed in the right tunnel of the Yunusabad metro line. This was reported in "Uzbekistan Temir Yullari".

The laying of engineering and communication systems, the docking of the existing Shahristan station complex and other events are scheduled to complete soon.

According to the company, more than 90% of the total amount of work has been completed so far. Construction is underway as scheduled, and the train is expected to run in test mode to Turkistan station by the end of the year.