Nasik, Jan. 13 -- Due to ongoing road widening (white topping) and valley side retaining wall construction work on the Saptashringi Gad to Nanduri road in Nashik, and to ensure smooth traffic flow and safety, an order has been issued to implement a one-way traffic system on the Saptashringi-Nanduri road from January 13, 2026, to March 15, 2026, according to a controlled schedule.

This order was issued by Assistant Collector and Sub-Divisional Officer (Kalwan) Dr. Kashmira Sankhe and PWD Superintendent Engineer Arundhati Sharma. This road passes through a hilly area, and due to its limited width, sharp turns, and steep inclines, two-way traffic is not technically feasible during the construction period. To ensure the quality and safety of t...