Hyderabad, July 31 -- Justice Pinakini Ghosh Commission on Thursday submitted its inquiry report on the Kaleswaram Multi-Level Lift Irrigation Project to Rahul Bojja, Principal Secretary of the Irrigation Department.

The report will now be forwarded to Chief Secretary K Ramakrishna Rao for further action.

The Commission, constituted by the Telangana government on March 14, 2024, probed the structural and operational issues in the Medigadda, Annaram, and Sundilla barrages over 15 months. During its inquiry, the panel questioned several people and recorded their statements.

The inquiry follows the sinking of piers at the Medigadda barrage in late 2023, along with seepage problems at the Annaram and Sundilla barrages. After the Congress gov...