, Aug. 31 -- The interim government has approved a one-year extension of a major project, 'BMR of Carew & Co (BD) Ltd (2nd Revised)', attributing the decision to the unavailability of experts amid shifting circumstances following August 5, 2024.

".the delay in the arrival of Indian experts due to the changing circumstances, it was not possible to conduct a trial run during the last threshing season," says the project document obtained by UNB.

The project period has been extended for the sixth time, without involving any additional costs, as the trial run of the newly installed machinery could not be completed in the last crushing season due to delays in the arrival of Indian experts.

The project, overseen by the Ministry of Industries ...