Pakistan, April 20 -- The Supreme Court on Friday expressed concern over the day in completion of the Orange Line Metro Train (OLMT) project, and instructed the construction companies concerned to finish work by May 20.

A two-member bench, headed by Justice Gulzar Ahmed, heard the case and demanded a guarantee of Rs 10 million each from the three construction companies involved in the project.

"The guarantees will be forfeited if the project is not finished by May 20," Justice Gulzar added, saying he hoped this project would be successful and not "come crashing down".

Justice Gulzar reprimanded the project's current director, Fazal Haleem, and said work had been delayed due to him. The court further directed that Justice (r) Jamshed or J...