Dhaka, May 5 -- Some power transformers were damaged in a fire at Bangladesh's only hydroelectric power substation in Rangamati's Kaptai on Sunday.

Md Shahadat Hossain, station officer of the Kaptai Fire Service, the fire originated at around 7:30 am on Sunday. Firefighters brought the fire under control around 8:30 am.

Engineer ATM Abduzzaher, managing director of the Kaptai hydroelectric power station, said the power suddenly went out during a thunderstorm.

Then, a transformer in the switchyard of the substation caught on fire when the line was restarted from the power plant.

He said they sent a proposal to the authorities to form a probe committee to find the extent of the damage caused by the fire.

Besides, the engineer noted tha...