Hyderabad, July 7 -- All five units of the Yadadri thermal power station (YTPS) are expected to be operational by February 2026, informed the Telangana Power Generation Corporation Limited (TGGENCO) on Monday, July 7.
The Yadadri thermal power plant built at Veerlapalem village, Dameracherla in Nalgonda district, is set to operate at 4000 MW with five units each supplying 800 MW of electricity.
Unit-2 was commissioned in January 2025 and Unit-1 is scheduled to be commissioned in July 2025. The remaining three units will be commissioned by February 2026.
The total coal requirement for all five units is estimated to be around 50,000 metric tonnes per day, which means the Singareni Collieries Company Limited (SCCL) would have to provide a...