SURKHET, Sept. 10 -- The work of the second package of 'Bheri-Babai Diversion Multipurpose Project', a national pride project, has started after four months of completion of tunnel construction. Under the second package, powerhouse, dam, and surge shaft will be constructed. The Department of Water Resources and Irrigation had signed an agreement with Raman-Guangdong JV on July 29, 2019 for the construction of the structures.

Prime Minister KP Sharma Oli had announced the breakthrough of 12.2 kilometers tunnel from Babai's Hattikhola to Bheri's Chiple in April. Tunnel Boring Machine (TBM) was used for the first time in Nepal for the construction of tunnel. China Overseas Engineering Group Company (COVEC) had completed the construction of tu...