Nepal, June 4 -- The new terminal building at Nepalgunj Airport is set to be completed ahead of the scheduled time. The construction is in its final phase, including Terminal Building Blocks A, B, and C, as well as the apron, vehicle parking, guest house, drainage, sidewalks, and toilets. The construction side claims that the project will be finished before the deadline.

Smita Punjali, the project engineer, said that the contractor company has accelerated the work to complete it ahead of the scheduled time.

The terminal building construction was started by Sharma and Company Pvt Ltd after signing the contract on December 16, 2022. According to the Nepalgunj Airport Project Office, the company agreed to complete all work by December 15, ...