Breakthrough achieved in Kaveli-3 Hydropower Project's first tunnel construction
TAPLEJUNG, Feb. 17 -- A 'breakthrough' has been achieved in the first tunnel of the Kaveli-3 hydropower project, with a capacity of 22 megawatts, currently under construction in Sirijanga Rural Municipality of Taplejung.
Meghnath Dhungana, the site in charge of the company, said that there was a breakthrough in the 182.10-meter-long tunnel of the Kaveli-3 hydroelectric power plant, promoted by Kaveli Hydropower Company Limited.
He mentioned that the construction of the tunnel, which began on May 24, will connect from the inlet to Audit-2. The estimated cost of the project, with a capacity of 21.93 megawatts, is Rs 4.3 billion, of which the loan investment from banks will be Rs 3.21 billion.
For the implementation of the plan, water wil...
Click here to read full article from source
To read the full article or to get the complete feed from this publication, please
Contact Us.