India, Jan. 8 -- The National Green Tribunal (NGT) on Wednesday said any document, including responses and reports, filed beyond the stipulated date, will be taken on record only after payment of costs.
The tribunal, while hearing a case about environmental violations in Haryana, noted that a joint committee failed to submit its final report by November last year, according to the green body's directions.
A bench of judicial member Arun Kumar Tyagi and expert member Afroz Ahmad said, "We have observed that despite orders passed by this tribunal specifying the period within which the counter-affidavits or reports are to be filed, the parties or committees concerned take liberty to file the same beyond the specified period, which causes u...