Manila, March 6 -- The Department of Transportation (DOTr) is processing the termination of its agreement with the contractor tapped to build the Unified Grand Central Station, also known as the Common Station that would link LRT1, MRT3 and MRT7 lines due to delays in the completion of the project.

In a statement on Thursday, DOTr Secretary Vince Dizon said the contractor, a consortium of BF Corp. and Foresight Development and Surveying Co. (BFC-FDSC), has left the construction idle for over a year.

"Our legal team is studying the termination of the contract so we can move on and finish this project," Dizon said in Filipino, calling the delay "unacceptable."

"This project should by now have been completed at napapakinabangan na ng mga ...