DALAT, April 23 -- The Public Works Department (JKR), along with the contractor, consultants, project licensee and other stakeholders involved in constructing the Kampung Medong/Lebrasau/Kampung Klid Road here, will meet on April 30 to discuss matters related to the completion of the 11.67-kilometre-long road.
In stating this, Deputy Premier Datuk Amar Douglas Uggah Embas emphasised the importance of the meeting in resolving issues affecting the project's progress.
He said that the RM74 million road project is a concern, as it is currently 70 days behind schedule, with only 48.56 per cent completion compared to the planned 55.62 per cent.
"That is why we always 'turun padang' (go to the ground) to check on the progress of project imple...