Dehradun, Jan. 28 -- THDC India Limited, a Mini-Ratna Public Sector Enterprise, has achieved a significant milestone with the commencement of commercial operations at Unit 1 of its 1320 MW Khurja Super Thermal Power Plant (KSTPP).
The Commercial Operation Date (COD) was officially declared at midnight on January 25, 2025, marking the company's successful expansion into thermal power generation alongside its traditional hydropower operations.
The project, which received its foundation stone from the Prime Minister of India, has successfully completed crucial operational milestones, including grid synchronisation, full load testing at 660 MW capacity, and a comprehensive 72-hour trial run.
The plant has met all regulatory requirements an...