India, Aug. 20 -- The Government of India issued the following news release:
The current status of infrastructure development at the Kulasekarapattinam spaceport, including the timeline for its full commissioning and the funds allocated and utilized for the project so far:
Land acquisition completed except for the land for rerouting the East-Coast Road.
Site development works completed and construction works commenced for technical facilities.
Fabrication of various equipment and structures is in progress at different work centres.
Commissioning of Kulasekarapattinam spaceport is targeted in FY 2026-27.
Funds allocated to Kulasekarapattinam spaceport - rs 985.96 Crore.
Fund utilized for the project so for - rs 389.58 Crore. (As on 31st Ju...