India, Dec. 3 -- The Government of India has issued a release:
The completion/ commissioning of Rajasthan Atomic Power Project, RAPP-8 (700 MW) is delayed mainly due to extensive design reviews and incorporation of new upgrades as a result of thorough analysis of the Fukushima accident in Japan. Another project, Kudankulam Nuclear Power Project, KKNPP-3&4 (2 X 1000 MW) has been delayed due to the ongoing Russia-Ukraine conflict and non-availability of rock products due to stoppage of quarry operations by district administration. In addition, financial crunch of contractors and impact of Covid 19 pandemic also contributed to delays in project execution.
The 500 MWe Prototype Fast Breeder Reactor at Kalpakkam, Tamil Nadu being commissioned ...