India, Feb. 11 -- The Government of India has issued a release:
Presently, the Mumbai-Ahmedabad High Speed Rail (MAHSR) Project (508 km) is under execution with technical and financial assistance from Government of Japan. The MAHSR project is planned and constructed on a elevated viaduct. The design for stations on the corridor provides for security measures like controlled entry points, baggage scanners, DFMDs (Door Frame Metal Detectors), CCTV(Close Circuit Television) cameras etc.
Item
Progress
Foundation
352 kms.
Piers
352 kms.
Girder Casting
342 kms.
Girder Launching
331 kms.
Track Bed Construction
152 kms.
OHE Masts Erection
121 kms.
Item
Progress
Foundation
74 kms.
Piers
65 kms.
Girder Casting
9 kms.
Girder La...