RANCHI, India, July 7 -- Jharkhand High Court issued the following order on June 6:

1. The instant writ petition has been filed under Article 226 of the Constitution of India for direction upon the respondents to pay the outstanding amount of Rs. 67.5 Lakh along with interest at the rate of 18 per cent per annum payable to the petitioner for supply of materials against Package 60 for Bhilai Steel Plant in relation to Purchase Order No. HEC/Proj/TRF-Pkg. 060 /BSP/08-1443 dated 24.07.2008 issued by Sr. DGM/Project Division, Heavy Engineering Corporation Limited along with the supervision work carried out by the petitioner for erection and commissioning of the New Coal Handling Plant at Bhilai Steel Plant (SAIL).

2. Learned counsel for the ...