RANCHI, India, July 7 -- Jharkhand High Court issued the following order on June 6:
1. The instant writ petition has been filed under Article 226 of the Constitution of India for direction upon the respondents for payment of admitted dues of work completed by the petitioner under the Scheme of Renovation of Senegarha Medium Irrigation.
2. Petitioner was awarded contract for repairing and renovation of Senegarha Medium Irrigation Scheme under Block Chanho for a value of Rs.88,94,568.91/- by Agreement No. 26/2017-18.
3. It is contended by learned counsel for the petitioner that the work was completed and yet the payment as per the agreement has not been made. Completion of work is evident from the letter No. 1306 dated 22.10.2019 issued ...