GUWAHATI, India, April 30 -- Gauhati High Court issued the following order on April 1:
1. Heard Mr. P. Mehta, learned counsel for the petitioner. Also heard Mr. A. Dasgupta, learned senior counsel assisted by Mr. G. Goswami, learned counsel for the respondent NF Railway.
2. Challenge made in this writ petition is to the termination notice dated 17.12.2020 issued by the Chief Engineer/Con-4, NF Railway, Maligaon, by which, the contract (LOA) is terminated and forfeited the Earnest Money Deposit, Bank Guarantee and Performance Guarantee to the tune of Rs.3,08,93,889.65 (Rupees three crores eight lakhs nine-three thousand eight hundred and eighty nine rupees sixty-five paise) and debarring the petitioner from participation in any and all te...