GUWAHATI, India, Nov. 30 -- Gauhati High Court issued the following order on Oct. 29:
1. The instant writ petition is filed by the petitioner challenging the non-payment of the admitted amount of Rs.3,00,000/- for completion of the work of "Renovation/Construction of ATMA/DAO Office, Kamrup under APART" to the petitioner by the Respondent Authorities.
2. The case of the petitioner herein is that the petitioner had completed the work awarded to him vide the work order dated 28.12.2021, i.e. "Renovation/Construction of ATMA/DAO Office, Kamrup under APART", as per the specifications, terms and conditions, and approved rate of CPWD Delhi Schedule of Rates, 2021 & CPWD E & M SOR, 2018 in the District of Kamrup, Guwahati, and he is entitled to...