India, Dec. 12 -- The Government of India has issued a release:
Period
Outlay
2009-14
Rs.108 crore/year
2025-26
Rs. 2716 Cr. (More than 25 times)
Bhanupalli-Bilaspur-Beri (63km) New Rail Line project has been sanctioned on cost sharing basis having 25% share of State Government of Himachal Pradesh and 75 % share of Central Government. Further, full cost of land beyond Rs. 70 crore is to be borne by Government of Himachal Pradesh. Detailed Estimate of the project was sanctioned at a cost of Rs. 6753 crore including land cost of Rs. 1617 crore.
In Himachal Pradesh, 124 Ha of land is required for the execution of the project. Against this requirement, only 82 Ha have been provided by State Government of Himachal Pradesh. Work has bee...