Gokhale bridge thrown fully open 30 months after closure
Mumbai, May 12 -- The southern arm of the reconstructed Gopal Krishna Gokhale bridge in Andheri was thrown open to traffic by cultural minister and Mumbai suburban guardian minister Ashish Shelar on Sunday, nearly 30 months after the closure of the bridge in November 2022. The southern arm of the CD Barfiwala flyover, which was misaligned with Gokhale bridge earlier, was simultaneously thrown open to traffic.
Local BJP MLA Ameet Satam, widely credited for accelerating the project's progress, shared the spotlight with Shelar during the inauguration ceremony which commenced at 5pm. In a light-hearted remark, the minister suggested that Satam should author a book titled "Gokhale Bridge: A Success Story", showcasing the reconstruction of the crucial east-west connector as an example of speedy development in the city.
Constructed in the 1960s, the Gokhale bridge was declared dilapidated in late 2018 after a portion of it collapsed, claiming two lives, and the Brihanmumbai Municipal Corporation (BMC) conducted a structural audit. Construction of a new flyover to replace the bridge commenced only in November 2021 and gathered pace after the old bridge was closed to traffic a year later, in November 2022.
Recollecting the chain of events on Sunday, Satam pointed to delays under the then Shiv Sena-led civic administration, which he claimed pushed reconstruction back by 20 months.
Once work commenced, the Lokhandwala Oshiwara Citizens Association (LOCA) played a key role in ensuring the project's progress by engaging with BMC officials and the local MLA and conducting frequent site visits. Involvement of Shiv Sena chief Eknath Shinde, who visited the site twice during his term as chief minister, also expedited matters. On February 27, 2024, barley 15 months after the bridge's closure, the northern carriageway was thrown open to traffic. But a controversy erupted soon after due to a 2.8-metre height difference between the new bridge and the adjacent CD Barfiwala flyover.
Abhijit Bangar, who assumed office as additional municipal commissioner (projects) in March 2024, took the lead in resolving the issue. The misalignment was corrected in a record 75 days and the northern arm of the Barfiwala connector was opened to traffic in July 2024.
"Despite multiple challenges, including delays by the railways in launching girders, the team worked tirelessly to meet the April 30 deadline," Bangar said on Sunday, recalling the chain of events. "In fact, we completed the project four days before the deadline."
While the inauguration was underway, HT saw workers undertaking minor patchwork on the northern arm of CD Barfiwala flyover, which was opened to traffic in July 2024.
"The patchwork was essential to prevent the emergence of potholes," said an official from BMC's roads department. "Some scratches were noticed on the flyover due to the stacking of steel girders used for supporting the old Gokhale bridge, which were rectified as per standard practice."...