NCRTC begins process to appoint general consultant
Gurugram, Nov. 1 -- In a major boost for the Delhi Gurugram Shahjahanpur-Behror (Delhi-SNB) regional rapid transit system (RRTS) project, the National Capital Region Transport Corporation (NCRTC) on Friday held a pre-bid meeting to appoint a general consultant for the project. The tender for hiring the general consultant was floated on October 10, and submission of bids will start from November 11 and it will close on November 18, the NCRTC said.
An NCRTC spokesperson said that a pre-bid meeting for the engagement of the general consultant for the project was held on Friday. At least 30 bidders participated. "The role of a General Consultant (GC) will be to act as the owner's or employer's representative to ensure that the project is planned, designed, and executed efficiently, safely, and within cost and time targets." The general consultant will provide advice on all aspects of project planning, design, procurement, and execution, as well as oversee the construction and execution of the civil and electrical works, the spokesperson said, adding that at present, pre-construction activities, such as road widening, geo-tech investigation, and utility shifting, have begun.
The Namo Bharat train will originate from Sarai Kale Khan, in south east Delhi, and end at Behror, in the NCR district of Alwar, while passing through Gurugram, as per the plan, which will be implemented in phases. The construction is expected to begin in August 2026 and the project is likely to be commissioned in November 2031, according to the new detailed project report (DPR) prepared by NCRTC earlier this year, and communicated to Haryana government in May this year. An estimated amount of Rs 35,000 crore will be spent on the 105 kilometres rapid rail system.
Under the new DPR, the NCRTC will select the general consultants for the project between December 2025 and May 2026; complete the land acquisition between December 2025 and November 2027; carry out a preliminary investigation and a detailed designing between December 25 to November 27; and the construction of the elevated structures will be carried out between August 2026 to August 2030.
The underground structures will be completed by January 2031, and track work, signalling work will be complete by June 2031....