Mohali, Oct. 22 -- National Highways Authority of India (NHAI) on Monday said that only 63% of work has been completed on the Rs.369-crore Chandigarh-Kharar flyover since the project began in November 2015.

In an RTI reply, project director KL Sachdeva said, "Till September, 63% of the work has been completed on the flyover."

As per an NHAI official, the completion of the 63% work includes building of the flyover structure from Khanpur to KFC T-point. "It also includes acquiring of 15 hectares of land and demolition of 440 structures out of the 500," he said.

Missing the two deadlines in the past, NHAI said that they are anticipating the completion of the flyover now by June 2020. The first deadline was December 2018 and second was March...